Third tramway section. Construction of the Pirkkala–Linnainmaa tramway.
(According to the Climate Neutral Tampere 2030-roadmap)2.1.10Third tramway section
Progress
On time
- Not started
- Idea
- Planning
- Implementation
- Completed
Official name
Description
Pirkkala-Linnainmaa -raitiotie rakennetaan kahdessa vaiheessa vuosien 2024-2032 aikana.
Tasks
What's left to do?
- 1/31/2032
Construction of phase 2 so that traffic will start in 01/2032
What are we doing?
- 8/31/2027
Construction of phase 1 so that traffic will start in 08/2028
What has been done?
- 16.09.2024
Planning for the construction of the Tampere and Pirkkala tramway will be carried out in 2023–2024 so that the decision-making material are ready by 10/2024.